730 promised homes at the West LA VA, checked against what actually opened

· nithan's blog

Dated, sourced record of the West LA VA veterans housing buildout against the VA's own November 2024 projection of 730 homes by end of 2025.

Compiled by Nithan, independent researcher. Last verified September 27, 2026. Corrections: nithan@ilands.app

In November 2024 the VA said 730 total units would be open on the West LA campus by the end of 2025. No VA release confirms that target was met on the promised date, or reports a year-end 2025 actual.

Best public confirmation of the number: the developer, not the agency. On Feb 3, 2026, The Veterans Collective announced Building 158 open with 48 furnished apartments and put the campus total at 729 permanent supportive housing units. One short of 730. About a month late.

And the VA's own latest figure: its July 2026 campus construction update says 729 completed as of July 1, 2026, 359 under construction, and 37 of those opening soon.

Correction, Sep 17, 2026 #

An earlier version of this record said the VA never published these numbers. That was wrong. VA Greater Los Angeles posted a campus construction update on its own channels in July 2026 giving 729 completed units as of July 1, 359 under construction, and 37 opening soon. Corrected here in place, dated.

What still holds: no VA release confirms the November 2024 "730 by the end of 2025" target was met on the promised date.

1. The dated chain #

Date Source What it says
Apr 2022 Master Plan Goal: at least 1,200 supportive housing units; 54 open at the time.
May 31, 2024 VA 233 open in 4 buildings; 374 under construction; "768 total ... surpassing halfway" to 1,200.
Sep 26, 2024 VA release Building 671 (MacArthur) opens, 74 units; campus 307 open; 7 buildings under construction (461 units); 768 projected.
Nov 14, 2024 VA "730 total units expected to be open by the end of 2025."
May 1, 2025 VHA bulletin Campus total 448 open. Same item slips the deadline: "730 expected to be open by 2026."
Jul 2025 Veterans Collective "About 750 homes completed or under construction." Open: B404 (72), B701 (118), B207 (59). Building: B158 (48), B156/157 (110).
Feb 3, 2026 TVC (Instagram) Building 158 officially open, 48 furnished apartments; campus total 729 PSH units.
Apr-May 2026 U.S.VETS Building 210 (women veterans): finishing touches; pre-leasing from May 19; opening "this summer."
May 20, 2026 Century Housing B156/157 = 112 homes; B404 = 73; B701 = 120.
May 28, 2026 VA release RFP for ~220 temporary units on the north campus. Capacity figures: 955 (Jan 2025) to 1,377 (May 2026) to 1,670 (end 2026) to 2,048 (2027).
Jul 2026 VA GLA Campus construction update: 729 completed as of Jul 1, 2026; 359 under construction; 37 opening soon.
Sep 11, 2026 LA Times Court order to build 1,800 permanent units and 750 transitional beds still stands on appeal; cost put at a record $1.25M per unit.

2. Building by building #

Building Units Status Basis
B404 72-73 Open By Jul 2025 (TVC; Century says 73)
B701 118-120 Open By Jul 2025 (TVC; Century says 120)
B207 59 Open By Jul 2025. Senior veterans.
B158 48 Open Feb 2026 (developer). Announced as 49 in May 2024.
B156/157 110-112 Under construction No dated opening found as of Sep 27, 2026.
B210 38 Not confirmed open U.S.VETS, women veterans. Pre-leasing from May 19, 2026; "opening this summer."
B300 + Town Center - Pre-development As of Jul 2025.

With B210 pending, the campus total lands near 767 if it opens. The master plan goal is 1,200.

3. Count discipline: where the numbers disagree #

Item Discrepancy
B158 Announced 49 (May 2024), opened 48 (Feb 2026).
B404 72 (TVC graphic) vs 73 (Century).
B701 118 (VA/TVC) vs 120 (Century).
B156/157 110 (TVC) vs 112 (Century).
Campus totals Differ by definition: 448 open (VA, May 2025) vs ~750 completed or under construction (TVC, Jul 2025) vs 729 total (TVC, Feb 2026). VA's last published campus-open figure is stale.
Sep 2026, two counts Vets Advocacy tracker: 766 completed, 321 under construction. VA GLA: 729 complete, 359 under construction. Off by 37.

The 37 looks like units counted open on one tally and still being built on the other. The one-unit gap between the two campus totals is unexplained. I do not guess it, and I do not know which count the VA treats as authoritative.

4. Sources #

Method #

Every figure above is dated and attributed. Where two public sources disagree, both are shown. Nothing here is inferred past what a named source says. If a source is wrong or a newer one exists, the record gets corrected in place and dated.

An interactive version of this record, with a filter for open and not-confirmed-open buildings, is at https://west-la-va-housing.surge.sh/